CNC Cycle Time Calculator

Work out how long a CNC part takes. Type the moves of the program with their feed rates, the rapid moves, the tool changes and the dwells, and see the time per part and the parts per hour. Other modes time a turning or facing cut, drilling with pecks, and gear hobbing.

Enter your values

Type the feed length and feed rate of each cut, the rapid moves, the dwells and the tool changes. The tool adds them up and gives the parts per hour.

Your values

The rapid traverse rate from the data sheet of your machine, in the unit chosen above.

The chip-to-chip time of your machine, or a time you measured.

Moves of the program

This unit is used in every row.

More options

Added to the time of the feed and rapid moves. Leave it empty to leave acceleration out.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Calculate.

How to use this calculator

  1. Choose what you want to time: a whole program, a turning or facing cut, holes drilled with pecks, or a hobbed gear.
  2. For a program, choose the unit of the rates (mm/min or in/min) and type the rapid rate and the time of one tool change of your machine.
  3. Type one row for each cut: the feed length of the tool path, its feed rate, the rapid length, any dwell, and tick the box when the row starts with a tool change.
  4. Choose Calculate. The table shows the time of every row; copy it or download it as a CSV file.

The formulas

  • Feed move: time = length of the tool path ÷ feed rate. Rapid move: time = length ÷ rapid rate.
  • Cycle time = cutting time + rapid time + dwell + number of tool changes × time of one change + loading and unloading (+ an allowance you type).
  • Parts per hour = 3600 seconds ÷ cycle time in seconds.
  • Turning: spindle speed n = Vc ÷ (π × D); feed rate = f × n; time of a pass = (L + approach) ÷ (f × n).
  • Facing at a constant cutting speed: the spindle speed rises as the tool moves in, n = Vc ÷ (2π × r), up to the limit n max. Time = π × (ro² − rc²) ÷ (f × Vc) + (rc − ri) ÷ (f × n max), with rc = Vc ÷ (2π × n max).
  • Pecks: k = depth ÷ peck depth, rounded up. With a full retract, feed distance = r + Z + (k − 1) × d, and every peck adds a rapid move up to the R plane and back down.
  • Hobbing: the gear blank turns at hob speed × starts ÷ number of teeth; time of a pass = (face width + approach) ÷ (axial feed per turn × blank speed).

Worked example

A milled part. Four cuts: 450 mm at 800 mm/min, 1200 mm at 1000 mm/min, 80 mm at 150 mm/min and 350 mm at 600 mm/min take 33.75 + 72 + 32 + 35 = 172.75 s. 1550 mm of rapid moves at 15,000 mm/min take 6.2 s. With 2 s of dwell, four tool changes of 6 s and 30 s to load the part, the cycle time is 234.95 s (3.92 min), or 15.32 parts per hour.

A turning pass. At 1200 rpm and 0.2 mm per turn the feed rate is 240 mm/min, so 80 mm plus 2 mm of approach take 82 ÷ 240 = 0.3417 min = 20.5 s. At a cutting speed of 180 m/min on a 50 mm diameter, n = 180,000 ÷ (π × 50) = 1145.9 rpm and the pass takes 21.47 s.

Facing to the centre a 50 mm bar at 180 m/min, 0.2 mm per turn, with a limit of 3000 rpm: the limit is reached at r = 9.549 mm. The cut takes 2.795 s at the constant cutting speed, 0.955 s at the limit, and 0.524 s for 2 mm of approach: 4.27 s.

Pecks. A 30 mm deep hole with 5 mm pecks needs 6 pecks. With the R plane 2 mm up and a clearance of 0.5 mm, the drill feeds 34.5 mm (17.25 s at 120 mm/min) and moves 199.5 mm in rapid (0.8 s at 15,000 mm/min).

Limits you should know

  • Acceleration and deceleration are left out: each move is taken at its full rate. Short moves take longer on a real machine, so check against a timed part or your CAM program, or type an allowance.
  • The lengths are the lengths of the tool path, not of the part. A CAM program or the program itself gives them.
  • Peck cycles work a little differently on each control; the clearance and the back-off are settings of the machine. Check the manual.
  • Feed rates, rapid rates, cutting speeds and tool change times come from your machine and tool data. Nothing is built in.
  • For the drill size of a tapped hole use the Tap Drill Size Calculator; for the stepover of a finishing pass use the CNC Stepover Calculator.