Check a recovery plan against your recovery time objective (RTO), see how much data your backup interval can lose against your recovery point objective (RPO), find how often to back up, and work out the cost of downtime. You type every figure; no objective is given as advice.

Enter your values

Add the steps of the recovery in order, in sequence or side by side, and compare the total with your recovery time objective.

Your values

The longest downtime your business accepts, from its own analysis.

Time to notice the outage and decide to start the recovery. Leave blank for none.

Recovery steps

One row for each step, in order. A step that starts at the same time as the step before runs side by side with it; the group takes as long as its longest step. Lengths come from your own tests of the plan.

This unit is used in every row.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Calculate.

RTO and RPO in plain words

  • Recovery time objective (RTO): the longest time a service may be down after a disaster before the harm is too great. It is a target, set by the business.
  • Recovery point objective (RPO): the most data, counted as time, that may be lost. An RPO of 1 hour means the last good copy may be at most 1 hour old.
  • Both come from your own analysis of the harm that downtime and lost data cause. This tool checks a plan against them; it does not say what they should be.

How to use this calculator

  1. Choose what you want to work out. Does a recovery plan meet the RTO? is the first choice.
  2. Type your RTO, and fill one row for each step of the recovery in order with its length from your own tests.
  3. For a step that runs at the same time as the step before, choose at the same time as the step before.
  4. Choose Calculate. The result says whether the plan meets the RTO and shows when each step starts and ends.

The formulas

  • Recovery time = time before the recovery starts + the length of each group of steps in turn. Steps side by side form a group, which lasts as long as its longest step.
  • Most data lost = time between backups + time until a backup is complete and safe. On average: half the time between backups + that time.
  • Longest time between backups for an RPO = RPO − time until a backup is complete and safe.
  • Cost of one outage = cost of one hour × hours down + cost for each outage. Money is rounded once to cents.

Worked examples

A plan: call the team (15 minutes), then start the standby servers (30 minutes) while the database is restored at the same time (90 minutes), then switch the traffic (10 minutes) and check the application (20 minutes). Recovery time = 15 + 90 + 10 + 20 = 135 minutes. Against an RTO of 4 hours that leaves 1 hour 45 minutes to spare.

Backups: a backup every 4 hours that takes 30 minutes to be complete and safe can lose up to 4.5 hours of data, 2.5 hours on average. An RPO of 6 hours is met with 1.5 hours to spare.

Frequency: for an RPO of 1 hour with 10 minutes until a backup is safe, back up at least every 50 minutes: 1,440 ÷ 50 = 28.8, so 29 backups a day.

Cost: 4 hours down at 5,000 an hour cost 20,000. With 2,500 for each outage that is 22,500, and 45,000 for 2 outages in a year.

Other tools for the same subject

Limits you should know

  • The plan is only as good as the step lengths you type. Take them from a real test of the recovery.
  • Steps run either after the step before or at the same time as it. More complex plans with several paths are not modelled.
  • The cost of downtime grows here in a straight line with time. Real costs often jump after a limit, such as a penalty in a contract.
  • This tool gives no objective as advice and is no replacement for a tested disaster recovery plan.