Sprint Capacity Calculator

Find how many hours your team can give to the next sprint. Type each person with the days they work in the sprint, their days off, their focus share and their hours a day. Add a past velocity to turn the capacity into a forecast in story points, and compare the planned work with it.

Enter your values

List the team with the days each person works in the sprint, days off, focus share and hours a day. Add a past velocity for a forecast in story points.

Your values

The average story points that the team finished in recent sprints.

The capacity in hours of the sprints the velocity comes from. Empty: the full capacity of this team with no days off is used.

The sum of the task estimates that the team plans to take into the sprint.

The story points of the items planned for the sprint. Needs a past velocity.

Team members

One row for each person. Working days in the sprint: the days that person works in this sprint (less for part-time work). Days off: leave, holidays and training. Focus share: the part of a working day that goes to sprint work after meetings and support, your own figure. The starting rows are an example.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Calculate.

How to use this calculator

  1. Choose Capacity of the team for a sprint.
  2. Add one row for each person: the working days in this sprint (5 for a part-time person in a two-week sprint, for example), the days off for leave, holidays or training, the focus share, and the hours in their working day.
  3. If you know the team velocity, type it. Type the capacity of the sprints it comes from as well, or leave that empty to compare with a sprint where nobody is away.
  4. Type the planned work in hours or in story points to see the load. Choose Calculate.
  5. To work out the velocity itself, choose Velocity and a forecast from past sprints and type the points finished in each past sprint.

The formulas

  • Capacity of a person = (working days in the sprint − days off) × hours a day × focus share ÷ 100.
  • Team capacity = the sum over the team. Full capacity is the same with no days off.
  • Forecast in story points = past velocity × team capacity ÷ the capacity of the sprints that velocity comes from (or the full capacity).
  • Load = planned work ÷ capacity × 100. Over 100% means more work than capacity.
  • Velocity = the average of the story points finished in past sprints. Sprints for a backlog = backlog ÷ velocity, rounded up.

Worked example

The starting team: Developer A works 9 of 10 days at 8 hours and 80% focus, which gives 57.6 hours. Developer B gives 64 hours, the tester 8 days × 8 × 75% = 48 hours, and the part-time designer 5 × 7.5 × 70% = 26.25 hours. The team capacity is 195.85 hours, and the full capacity with no days off is 214.25 hours.

With a past velocity of 34 points, the forecast is 34 × 195.85 ÷ 214.25 = 31.08 points. A plan of 30 points is 96.5% of that, and 180 planned hours are 91.9% of the capacity.

Velocity: sprints of 30, 34, 28, 36 and 33 points give an average of 32.2. With 42 person-days this sprint against 50 in a usual one, the forecast is 32.2 × 42 ÷ 50 = 27.05 points, and a backlog of 200 points needs 8 sprints (7 at the highest velocity, 9 at the lowest).

Limits you should know

  • The days, hours, focus shares and velocity are your own figures. The tool has no standard focus share. The result is your figures combined by the stated rule, not a promise of what the team will finish.
  • Story points belong to one team. The forecast only scales its own past velocity; it does not change hours into points by a fixed rate.
  • Working days are typed, not counted from a calendar. To count working days between two dates with holidays, use the Project Duration Calculator or the Date Calculator.
  • The tool does not plan the sprint backlog item by item.