Task Estimate Calculator
Type three values for each task: the optimistic, the most likely and the pessimistic time or cost. The calculator gives the PERT mean and standard deviation, the triangular mean beside it, and for a list of tasks a total with a range at the confidence level you choose.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose One task or Several tasks, and the unit that your numbers are in. The unit is a word for the results only.
- Type the optimistic value (O), the most likely value (M) and the pessimistic value (P). O must not be more than M, and M must not be more than P.
- For several tasks, add one row for each task, or paste a list copied from a spreadsheet into Paste a task list and choose Read into rows.
- Choose a confidence level, such as 80% or 90%. You can also type a target, such as the hours you have, to see the chance of finishing within it.
- Choose Calculate. Download the tables as a CSV file, copy the result or print it.
The formulas
- PERT mean (also called the beta or weighted mean) = (O + 4 × M + P) ÷ 6.
- PERT standard deviation = (P − O) ÷ 6. The variance is its square.
- Triangular mean = (O + M + P) ÷ 3. Its standard deviation is √((O² + M² + P² − OM − OP − MP) ÷ 18).
- Total of several tasks: the means add up, and the variances add up. The standard deviation of the total is the square root of the summed variances.
- Value at a confidence level c = mean + z × standard deviation, where z is the point of the standard normal distribution with c of the outcomes below it (z = 1.2816 for 90%). This is the normal approximation.
- Central range = mean ± z × standard deviation, with z for (1 + c) ÷ 2. Chance of a target T = the normal distribution at (T − mean) ÷ standard deviation.
Worked example
One task: O = 2, M = 4 and P = 9 hours. The PERT mean is (2 + 16 + 9) ÷ 6 = 4.5 hours, and the standard deviation is (9 − 2) ÷ 6 = 1.1667 hours. The triangular mean is 15 ÷ 3 = 5 hours. At 90% confidence the estimate is 4.5 + 1.2816 × 1.1667 = 5.995 hours, and the chance of finishing within 6 hours is 90.1%.
Five tasks (the starting rows): the most likely values add up to 35 hours, but the PERT means add up to 38.667 hours. The variances add up to 17.278, so the standard deviation of the total is 4.157 hours. At 90% confidence the total is 43.99 hours, the central 90% range runs from 31.83 to 45.50 hours, and the chance of finishing within 45 hours is 93.6%.
Limits you should know
- The results are your own three values combined by the stated rules. They are not a promise of a date or a cost.
- The range of the total assumes that the tasks do not depend on each other. Tasks that run late for the same reason make the real range wider.
- The normal approximation is better with many tasks. For one task, or a few tasks with a long pessimistic side, read the range as a rough guide.
- The unit is a word only. Use one unit for every value in a list; nothing is converted.
- The tool does not order tasks or find the critical path of a network. For steps that follow each other, use the Workflow Builder.