Project Effort Calculator
Work out the effort and the cost of a project from your own figures. List the tasks or work packages with a quantity and the effort for one unit, scale the effort of a past project to a new size, or check a running project with earned value. Results come by row, by phase and by role.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose Effort and cost from tasks or work packages to build the estimate from the bottom up.
- Choose whether you type the effort in hours or in days, and the hours in your working day.
- Add one row for each task or work package. Type how many units it has (screens, rooms, test cases, weeks) and the effort for one unit. Add a phase and a role to see the totals by phase and by role, and a rate and other costs to see the cost. You can paste the rows from a spreadsheet.
- If you like, type a productive share (the part of a working day that goes to this work) and an overhead share (management and reviews on top). Leave them empty to use the effort as typed.
- Choose Calculate. Download the tables as a CSV file, copy the result or print it.
- To scale from a finished project, choose Scale from a past project. To check a running project, choose Earned value.
The formulas
- Effort of a row = quantity × effort per unit × factor. Factor = 100 ÷ productive share × (1 + overhead share ÷ 100). Days = hours ÷ hours in a working day.
- Labour cost of a row = effort in the unit you typed × the rate per hour or per day of that row, rounded to cents. Other costs are added as typed. Every total is the sum of its rows.
- Analogous estimate = past effort × (new size ÷ past size) × (1 + adjustment ÷ 100). The same scale is used for the cost.
- Earned value: PV = planned value, EV = earned value, AC = actual cost. SV = EV − PV, CV = EV − AC, SPI = EV ÷ PV, CPI = EV ÷ AC.
- Forecasts: EAC = BAC ÷ CPI, ETC = EAC − AC, VAC = BAC − EAC, TCPI = (BAC − EV) ÷ (BAC − AC). Two other common forms of EAC are AC + (BAC − EV) and AC + (BAC − EV) ÷ (CPI × SPI).
Worked example
The starting rows hold 264 hours of work: 3 workshops of 6 hours, 12 screens to design at 4 hours, 12 screens to build at 10 hours, 60 test cases at 0.5 hours and 8 weeks of management at 6 hours. With 8 hours in a working day that is 33 person-days. With the rates in the rows the labour cost is 19,950.00, and with 1,200.00 of licences the total cost is 21,150.00.
With a productive share of 85% and an overhead share of 10%, the factor is 100 ÷ 85 × 1.1 = 1.2941, and the effort becomes 341.65 hours or 42.71 person-days.
Analogous: a past project of 40 screens took 1,200 hours. A new project of 55 screens is 1.375 times the size, so it needs 1,650 hours; with 10% added for harder work, 1,815 hours.
Earned value: a budget of 100,000, 50% planned and 40% done, with 45,000 spent. PV = 50,000 and EV = 40,000. SPI = 0.8 and CPI = 0.889, so the estimate at completion is 100,000 ÷ 0.889 = 112,500 and the work needs 67,500 more.
Limits you should know
- Every quantity, effort, rate and share is your own figure, and the starting rows are only an example. The tool has no benchmark for how long work takes. The result is your figures combined by the stated rules, not a promise of a date or a cost.
- The rows are added as they are. The tool does not find work that two rows both hold, or work that is missing.
- Effort is not duration. To turn effort into a finish date with the people you have, use the Project Duration Calculator.
- For a range from optimistic and pessimistic values, use the Task Estimate Calculator. For a reserve on top of the estimate, use the Estimate Contingency Calculator.
- Building work with material quantities belongs in the Construction Cost Calculator.