Estimate Contingency Calculator
Find a contingency reserve for an estimate in money or in time. Choose one of three methods: a share of the estimate, the spread of a three-point estimate at the confidence you choose, or the expected value of a list of risks. Add a management reserve as a separate share and see the total budget.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose a method in the first list, and the unit of your estimate: money, hours, days or weeks.
- A share of the estimate: type the estimate and the contingency share that you want.
- From the spread of a three-point estimate: type each part of the estimate with an optimistic, a most likely and a pessimistic value, or paste them from a spreadsheet. Choose what your base estimate is and the confidence level, such as 80%.
- From a list of risks: type the estimate, then each risk with its chance in percent and the cost or time it would add.
- If you keep a management reserve, type its share and choose what it is a share of. Choose Calculate, then download the tables as a CSV file or print the result.
The three methods
- Share of the estimate: contingency = estimate × share ÷ 100.
- Three-point spread: for each item, PERT mean = (O + 4 × M + P) ÷ 6 and standard deviation = (P − O) ÷ 6. The means add up, and so do the variances. The total at a confidence level c is mean + z × standard deviation, with z from the normal distribution (z = 0.8416 for 80%). Contingency = that total − your base estimate, and 0 when the base already reaches it.
- Expected value of risks: expected value of a risk = probability ÷ 100 × impact. Contingency = the sum of the expected values.
- Management reserve = its share × the estimate, or × the estimate plus the contingency, as you choose. It is kept apart from the contingency.
- Total budget = estimate + contingency + management reserve. Total reserve = contingency + management reserve.
Worked example
A share: an estimate of 50,000 with a 10% contingency gives 5,000, so the estimate with contingency is 55,000. A management reserve of 5% of that is 2,750, and the total budget is 57,750. The total reserve is 7,750, or 15.5% of the estimate.
A three-point spread (the starting rows): the most likely values add up to 44,000 and the PERT means to 46,833.33. The standard deviation of the total is 3,662.88. At 80% confidence the total is 46,833.33 + 0.8416 × 3,662.88 = 49,916.09, so the contingency over the most likely sum is 5,916.09.
A list of risks (the starting rows): 30% × 8,000 + 50% × 5,000 + 10% × 15,000 + 20% × 2,000 = 2,400 + 2,500 + 1,500 + 400 = 6,800. On an estimate of 50,000 that is 13.6%. If every risk happened, they would add 30,000.
Limits you should know
- The shares, chances, values and confidence level are your own. The results combine them by the stated rule. They are not a promise of a cost or a date, and no share is a rule of any standard.
- The three-point method assumes that the items do not depend on each other and uses the normal approximation. Items that run over for the same reason make the real range wider.
- The expected value is an average. A large risk that happens costs its whole impact, which can be more than the reserve.
- The risk list is for threats only. A chance to save money is not taken off the reserve.
- In money, each line is rounded to whole cents and each total is the sum of its rounded lines. A time unit is a word only and nothing is converted.