Toolvito

Works on this device

Operations Performance Calculator

Work out common measures of operations from your own times and counts: availability and down time, overall equipment effectiveness (OEE), on-time and first-pass rates, maintenance backlog, the cost of down time, an equipment criticality matrix, a Pareto of causes and a process audit score. Each result states its formula.

Enter your values

Down time and availability of a line, a machine or a team from the scheduled time and the stops.

Your values

All the time the line, machine or team was scheduled, for example 2 shifts of 8 hours on 5 days is 80 hours.

Stops

One row for each reason, with the total time of all its stops. Down time: breakdowns, changeovers, waiting for material, and other stops while production was planned. Planned shutdown: breaks, planned maintenance and other time with no production planned. It is taken out of the planned production time.

This unit is used in every row.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Calculate.

How to use this calculator

  1. Choose the measure from the list.
  2. Enter your times, counts and figures. Times have a unit list; choose minutes, hours or days.
  3. Choose Calculate. The result shows the measure, the numbers it came from and the formula.
  4. Copy the result, print it or download it as a CSV file.

The formulas

  • Availability = run time ÷ planned production time. Planned production time = scheduled time − planned shutdowns, and run time = planned production time − down time.
  • OEE = availability × performance × quality. Performance = ideal cycle time × total count ÷ run time. Quality = good count ÷ total count. So OEE = good count × ideal cycle time ÷ planned production time.
  • On-time delivery rate = orders delivered on time ÷ orders delivered. First-pass yield = units right the first time ÷ units that entered the step. Preventive maintenance compliance = tasks done on time ÷ tasks scheduled. Planned maintenance share = planned maintenance hours ÷ all maintenance hours.
  • Backlog in weeks = backlog hours ÷ (people × hours each in a week × share of their time for this work).
  • Cost of down time = margin of the lost output + people who wait × their hourly cost × hours + other hourly costs × hours + one-time costs.
  • Criticality score = the highest of four consequence ratings × the likelihood of failure, each from 1 to 5.
  • Pareto: causes in order of count, with the share and the running share of the total.
  • Audit score = points given ÷ the most points possible, for the items that were scored.

Worked example

Availability: 80 scheduled hours with 300 minutes of breaks leave 4,500 minutes of planned production time. Breakdowns (150 minutes), changeovers (200) and waiting for material (70) make 420 minutes of down time, so availability is 4,080 ÷ 4,500 = 90.67% and the down time share is 9.33%.

OEE: a planned production time of 420 minutes, 47 minutes of down time, an ideal cycle time of 1 second, 19,271 units made and 18,848 good units give availability 88.81%, performance 86.11%, quality 97.80% and OEE 74.79%.

Cost of down time: 6 hours with 120 units not made in each hour at a margin of 4.50 (3,240.00), 5 people at 32 an hour (960.00) and 850.00 of one-time costs make 5,050.00, which is 841.67 for each hour.

Limits you should know

  • No benchmark, target or "world class" figure is built in. Compare with your own targets and your own earlier results.
  • Mean time between failures and mean time to repair are not worked out here. They have their own tools, the Mtbf Calculator and the Mttr Calculator.
  • The criticality matrix is one simple scheme: the highest consequence × likelihood. Your site may use weights or other scales.
  • The result is as good as the times and counts you enter. Record stops and counts the same way in every period that you compare.

Related tools