Overall equipment effectiveness (OEE) shows how much of the planned production time made good units at full speed. Enter your times and counts to get availability, performance, quality and OEE, and see where the time was lost.

Enter your values

Availability, performance, quality and OEE from the planned time, the down time, the ideal speed and the counts.

Your values

From the start to the end of one shift, with its breaks. At most 24 hours.

Meal and rest breaks, meetings, planned cleaning and planned maintenance: time in the shift when no production is planned.

Shifts in the period you measure, for example 1 for one shift or 5 for a week of one shift a day.

Stops while production was planned: breakdowns, set-ups, changeovers and adjustments, waiting for material.

The fastest time in which one unit can be made, from the design or the name plate of the machine.

Units made right the first time, with no rework and no scrap.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Calculate.

How to use this calculator

  1. Choose OEE from times and counts, OEE from availability, performance and quality or Overall labour effectiveness (OLE).
  2. Enter the planned production time, or the length of the shift with its breaks. Enter the down time while production was planned.
  3. Enter the ideal speed of the machine as an ideal cycle time or as an ideal run rate, then the total count and the good count.
  4. Choose Calculate. The result shows the three factors, OEE, the working and a table of where the time went.

The formulas

  • Planned production time = shift time − planned breaks and planned stops.
  • Availability = run time ÷ planned production time, where run time = planned production time − down time.
  • Performance = ideal cycle time × total count ÷ run time. Ideal cycle time = 1 ÷ ideal run rate.
  • Quality = good count ÷ total count. A good unit is right the first time: a unit that needed rework is not good here.
  • OEE = availability × performance × quality = good count × ideal cycle time ÷ planned production time.
  • Overall labour effectiveness uses the same three factors for the time of people: working time ÷ scheduled time, standard time × units ÷ working time, and good units ÷ units.

Worked example

A shift of 8 hours has 40 minutes of planned breaks, so the planned production time is 440 minutes. The machine was down for 50 minutes, so it ran for 390 minutes. Its ideal cycle time is 1.5 seconds (40 units a minute). It made 13,200 units, and 12,800 were right the first time.

Availability = 390 ÷ 440 = 88.64%. Performance = 1.5 × 13,200 ÷ (390 × 60) = 19,800 ÷ 23,400 = 84.62%. Quality = 12,800 ÷ 13,200 = 96.97%. OEE = 88.64% × 84.62% × 96.97% = 72.73%, the same as 12,800 × 1.5 ÷ 26,400 seconds.

The six big losses

The six big losses of total productive maintenance (TPM) are a common way to group the lost time under the three factors. The table of the result uses them.

  • Availability: breakdowns; set-ups and adjustments.
  • Performance: idling and small stops; reduced speed.
  • Quality: start-up rejects; production rejects (scrap and rework).

Related tools

Limits you should know

  • No benchmark is built in. A figure of 85% is often quoted as "world class"; it is a commonly quoted benchmark, not a standard. Compare with your own earlier results.
  • A performance above 100% usually means that the ideal cycle time is too long. Use the true fastest speed of the machine.
  • OEE counts only the planned production time. Time with no production planned is not a loss here.
  • Sites count some stops in different ways, such as planned maintenance or changeovers. Use one rule in every period that you compare.

Related tools