Production Capacity Calculator
Find how many units your machines or work places can make in a shift, a day or any period, which step of a line holds the output back, and how many machines a demand needs. Every figure is your own.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose what you want to work out: Design and effective capacity, Capacity of a line and its bottleneck or Machines needed for a demand.
- Enter the speed of a machine as units in one hour, as the time for one unit, or as a batch with its set-up time.
- Enter your shifts, breaks and working days, or the running time of the line. Choose the unit of each time.
- Choose Calculate. The result shows each figure and how it was worked out. You can copy it, print it or download it as a CSV file.
The formulas
- Design capacity = machines × units one machine makes in one hour × scheduled hours. Scheduled hours = length of a shift × shifts each day × working days.
- Effective capacity = machines × units in one hour × available hours. Available hours = (length of a shift − breaks and planned stops) × shifts. These are the terms of operations management textbooks.
- Expected output = effective capacity × your expected efficiency. It is shown only when you type an efficiency.
- Speed: units in one hour = 3,600 ÷ seconds for one unit, or units in a batch ÷ hours for the batch with its set-up.
- Capacity of a step = machines at that step × units one machine makes in one hour. Capacity of a line = the capacity of its slowest step, the bottleneck.
- Machines needed = units needed × time for one unit ÷ (available time of one machine × efficiency), rounded up to a whole machine.
Worked example
Four machines each make 60 units in one hour. They run 2 shifts of 8 hours a day with 30 minutes of breaks in each shift, on 5 days. Scheduled time is 8 × 2 × 5 = 80 hours, so the design capacity is 4 × 60 × 80 = 19,200 units. Available time is 7.5 × 10 = 75 hours, so the effective capacity is 4 × 60 × 75 = 18,000 units. With an expected efficiency of 85%, the expected output is 15,300 units.
A line has five steps. Welding has 3 machines that each need 75 seconds for one unit, so it makes 3 × 3,600 ÷ 75 = 144 units in one hour. Every other step makes more, so welding is the bottleneck. In 75 hours of running the line makes 144 × 75 = 10,800 units.
To make 12,500 units of 45 seconds each, the machines need 156.25 hours of work. One machine has 75 hours, so 156.25 ÷ 75 = 2.08 machines are needed: 3 machines, each loaded to 69.44%.
Related measures
- Capacity utilization, actual output ÷ capacity: Capacity Utilization Calculator.
- The time for one unit and the cycle time of a line: Cycle Time Calculator. The pace that the demand sets: Takt Time Calculator.
- Losses while a machine runs: Overall Equipment Effectiveness Calculator.
Limits you should know
- The speeds, times and efficiency are your own figures. No typical value or benchmark is built in.
- Capacity assumes one product, or a mix with the same time for each unit. Several products with different times and set-ups need a capacity for each product.
- The bottleneck view assumes that every unit goes through every step once, with no scrap, no rework and no waiting between steps.
- This is a planning estimate. It is not a schedule: it does not put orders in an order or give dates.