Takt time is the pace that customer demand sets: the time in which one unit must be finished. Enter your shifts and the demand to get it, and find how many stations or operators the work needs at that pace.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose Takt time from available time and demand or Stations or operators for a takt time.
- For takt time, enter the length of a shift, the breaks and planned stops in each shift, the shifts in the period and the demand in the same period.
- For stations, list the tasks of one unit with their times, and enter the takt time.
- Choose Calculate. Copy, print or download the result as a CSV file.
The formulas
- Takt time = available time ÷ customer demand.
- Available time = (length of a shift − breaks and planned stops) × shifts in the period.
- Fewest stations or operators = work content ÷ takt time, rounded up. Work content is the sum of the task times of one unit.
- Balance efficiency = work content ÷ (stations × takt time). Idle time in each cycle = stations × takt time − work content.
Worked example
A line runs 2 shifts of 8 hours with 30 minutes of breaks in each shift, and the customers need 900 units a day. Available time = (8 h − 0.5 h) × 2 = 15 hours = 54,000 seconds. Takt time = 54,000 ÷ 900 = 60 seconds. One unit must be finished every minute.
The tasks of one unit take 25, 40, 18, 32, 45, 22 and 30 seconds: 212 seconds of work content. At a takt time of 60 seconds that is 212 ÷ 60 = 3.53, so at least 4 stations are needed. Balance efficiency = 212 ÷ (4 × 60) = 88.33%, and 28 seconds of each cycle are idle.
Takt time and cycle time
Takt time comes from the demand. Cycle time is the time your process really needs for one unit. To meet the demand, the cycle time must be at or below the takt time. Type your cycle time in the first part to compare. To work out a cycle time, use the Cycle Time Calculator.
Limits you should know
- Use the same period for the shifts and the demand, such as one day or one week.
- The number of stations is a lower limit. The order of the tasks and their sizes can make more stations necessary. Putting the tasks into stations is not done here.
- A task that is longer than the takt time needs two or more stations side by side, or must be split.
- The times and the demand are your own figures. Nothing is built in.