Cycle Time Calculator
Cycle time is the time from one finished unit to the next. Work it out from the time and the units made, from cycles you timed, or for a whole line from its stations. You can also work out the lead time of a batch.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose what you want to work out.
- Cycle time from time and units: choose what to find, then enter the other two. You can also find the units made in a time, or the time for a number of units.
- Average of timed cycles: type the time of each cycle you timed.
- Cycle time of a line: list the stations with the time for one unit and the people or machines side by side.
- Manufacturing lead time: list the operations of a batch, or enter the work in progress and the throughput.
- Choose Calculate. Copy, print or download the result as a CSV file.
The formulas
- Cycle time = production time ÷ units made. Units per hour = 3,600 seconds ÷ cycle time in seconds.
- Average cycle time = sum of the timed cycles ÷ number of cycles.
- Cycle time of a station = time for one unit ÷ people or machines side by side. Cycle time of a line = the longest station cycle time. That station is the bottleneck.
- Balance efficiency = work content ÷ (people or machines in all × cycle time of the line).
- Manufacturing lead time of a batch = Σ (set-up time + units in the batch × time for one unit + time between operations).
- Lead time by Little's law = work in progress ÷ throughput.
Worked example
A machine ran for 7.5 hours and made 540 units. Cycle time = 27,000 seconds ÷ 540 = 50 seconds, which is 72 units an hour.
A line has stations of 42, 55, 96, 58 and 30 seconds, and two welders share the 96-second station, so its cycle time is 48 seconds. The longest station cycle time is 58 seconds (Assemble), so the line makes 3,600 ÷ 58 = 62.07 units an hour. The work content is 281 seconds for 6 people: balance efficiency = 281 ÷ (6 × 58) = 80.75%.
A batch of 50 units goes through three operations. Cut: 30 minutes set-up, 0.8 minutes a unit and 4 hours of waiting. Bend: 45 minutes, 1.2 minutes and 6 hours. Paint: 20 minutes, 0.5 minutes and 8 hours. Lead time = (30 + 40 + 240) + (45 + 60 + 360) + (20 + 25 + 480) = 1,300 minutes, about 21.67 hours.
Cycle time, takt time and lead time
- Cycle time is how often the process finishes a unit. Takt time is how often the customers need one: Takt Time Calculator. To meet the demand, the cycle time must be at or below the takt time.
- Some operations textbooks call available time ÷ output needed the "cycle time" of a line. It is the same division as the first part of this tool.
- Lead time is how long one unit or batch takes from start to end, waiting included. Value-added time as a share of the lead time and Little's law in every direction are in the Lean Process Calculator.
- Machining time of a CNC part from feeds and speeds: CNC Cycle Time Calculator.
Limits you should know
- The times and counts are your own figures. No typical cycle time is built in.
- The line view assumes that every unit goes through every station once and that the stations do not wait for each other.
- The lead time of a batch assumes that the whole batch finishes an operation before it moves on. It is in working time when your times are working times.