Three lean measures in one place: how much of the lead time adds value, how work in progress, throughput and lead time hang together by Little's law, and how many kanban cards a pull loop needs.

Enter your values

The share of the lead time that adds value, from the steps of a process or from two totals.

Your values

Steps of the process

One row for each step from start to end, waiting included. Value-added: work that changes the product in a way the customer pays for. Needed, not value-added: work the business needs now, such as an inspection required by law. Waste: waiting, moving, extra handling, rework.

This unit is used in every row.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Calculate.

How to use this calculator

  1. Choose Process cycle efficiency, Little's law or Number of kanban cards.
  2. For process cycle efficiency, list the steps of the process from start to end with their times, and mark each one as value-added, needed or waste. Or type the two totals.
  3. For Little's law, choose what to find and enter the other two figures in one time unit.
  4. For kanban cards, enter the demand, the replenishment lead time, a safety factor and the units in one container.
  5. Choose Calculate. Copy, print or download the result as a CSV file.

The formulas

  • Process cycle efficiency (PCE, the value-added time ratio) = value-added time ÷ total lead time × 100.
  • Little's law: work in progress = throughput × lead time. So lead time = work in progress ÷ throughput.
  • Kanban cards = demand × replenishment lead time × (1 + safety factor) ÷ units in one container, rounded up.

Worked example

An order waits 48 hours for material, is cut in 0.5 hours, waits 16 hours, is welded in 1.2 hours, inspected in 0.3 hours, waits 24 hours, is painted in 0.8 hours and packed in 0.4 hours. The lead time is 91.2 hours and the value-added time is 0.5 + 1.2 + 0.8 = 2.5 hours. PCE = 2.5 ÷ 91.2 = 2.74%.

A plant has 1,200 units of work in progress and finishes 300 units a day. Lead time = 1,200 ÷ 300 = 4 days.

A part is used at 500 a day, a container holds 40 and it takes 2 days to refill. With a safety factor of 10%: 500 × 2 × 1.1 ÷ 40 = 27.5, so 28 kanban cards.

Related lean measures

Limits you should know

  • PCE depends on how you mark each step. Mark the steps in the same way when you compare.
  • Little's law holds for averages over a long, steady time. It does not give the longest wait of one unit.
  • The kanban formula gives a starting number of cards. Watch the loop and change the number when the demand or the lead time changes.
  • No benchmark is built in. Drawing a value stream map is not done here.