Production Efficiency Calculator

Compare what was made with what a standard says it should take. Work out labour efficiency from standard times and hours worked, or the efficiency of a machine or line against its standard rate.

Enter your values

Standard hours earned by the units made ÷ the hours worked, for a team, a line or a factory.

Your values

Operators on the line or in the team. Part-time people may be counted as parts of one.

Paid working time in the period, less planned breaks.

Your standard cost of one hour of labour, to work out the labour efficiency variance.

Work done

One row for each product, style or operation with its units made and its standard time (in the garment trade the standard allowed minutes, SAM).

This unit is used in every row.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Calculate.

How to use this calculator

  1. Choose Labour efficiency from standard times or Output against a standard rate.
  2. For labour efficiency, list each product or operation with the units made and its standard time for one unit. Enter the people and their working time, or the hours worked in all.
  3. For a standard rate, enter the actual output, the standard output in one hour and the running time.
  4. Choose Calculate. Copy, print or download the result as a CSV file.

The formulas

  • Standard hours earned = Σ units made × standard time for one unit.
  • Labour efficiency = standard hours earned ÷ hours worked × 100.
  • In the garment trade: efficiency = output × SAM ÷ (operators × working minutes) × 100, where SAM is the standard allowed minutes of a garment.
  • Labour efficiency variance = (standard hours earned − hours worked) × standard labour rate. Above 0 is favourable.
  • Efficiency against a standard rate = actual output ÷ (standard output in one hour × running time) × 100.

Worked example

A sewing line of 25 operators works 8 hours: 200 hours, or 12,000 minutes. It makes 450 shirts with a SAM of 15 minutes and 300 polo shirts with a SAM of 9.5 minutes: 6,750 + 2,850 = 9,600 standard minutes, which is 160 standard hours. Efficiency = 160 ÷ 200 = 80.00%.

A machine should make 200 units an hour. In 7.5 hours of running it made 1,380 units against a standard of 1,500. Efficiency = 1,380 ÷ 1,500 = 92.00%.

Efficiency and OEE

Production efficiency compares output with a standard time or rate. Overall equipment effectiveness (OEE) multiplies availability, performance and quality of a machine. For OEE use the Overall Equipment Effectiveness Calculator. For actual output ÷ capacity use the Capacity Utilization Calculator.

Limits you should know

  • The result is only as good as the standard times. A standard that is too loose gives an efficiency above 100%.
  • Count the hours in the same way in every period you compare: with or without waiting time, meetings and training.
  • No typical efficiency is built in.