Concrete Quantity Calculator
Find the volume of concrete for a slab, footing, wall, column, post hole, steps or curb. The result shows cubic yards, cubic metres and cubic feet, the number of bags, the weight, and the cost if you type a price.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose the shape that you want to pour, for example Slab, pad, floor, driveway or patio.
- Type each size and pick its unit. You can mix units, such as feet for the length and inches for the thickness.
- Set Extra for waste. Many people add 5 to 10 percent for spills and uneven ground.
- Choose the weight of the bags that you plan to use, such as 80 lb or 20 kg.
- Choose Calculate. Open More options to type a bag yield, a density or a price.
What each option does
- Slab, pad, floor, driveway or patio: a flat pour that is a rectangle, a circle or a triangle, or an area that you already know. A thickened edge can be added.
- Footing, beam or trench: any straight block, from length × width × depth.
- Trapezoidal strip or tapered rectangular footing calculates concrete from the lower and upper dimensions and the vertical height between them. Enter a flat base separately if the footing has one.
- Wall: length × height × thickness. Openings are not taken off.
- Column, pier or tube form: round or rectangular columns, deck piers, piles and cardboard tube forms.
- Post hole: a round hole, less the space taken by the post.
- Steps or stairs: solid steps on the ground, or a stair slab that spans between floors.
- Hollow tube, pipe or ring and Curb and gutter cover two more common shapes.
- Bags, weight and cost for a known volume starts from a volume in cubic feet, yards or metres.
- What one bag of concrete makes shows the yield of a bag, bags per cubic yard and the area a bag covers.
- Cement, sand and stone for a mix ratio is for concrete that you mix yourself.
The formulas
- Rectangular slab, footing or wall: volume = length × width × thickness.
- A straight-sided rectangular taper has volume equal to its vertical height times (bottom area + 4 × halfway area + top area) ÷ 6. The halfway lengths are the averages of the matching top and bottom lengths. A rectangular base beneath the slope adds bottom area × base thickness.
- Round slab or column: volume = π × diameter² ÷ 4 × thickness or height.
- Post hole: volume = (area of the hole − area of the post) × depth.
- Solid steps: volume = width × run × rise × (1 + 2 + … + number of steps).
- Volume to order = volume × (1 + waste percent ÷ 100).
- Bags = volume to order ÷ yield of one bag, rounded up. One cubic yard is 27 cubic feet, or 0.7646 cubic metres.
- Weight = volume × density. Normal concrete is about 150 lb per cubic foot, or 2,400 kg per cubic metre.
- Mix ratio: dry volume = finished volume × dry volume factor. Each material gets its share of the dry volume, in line with the ratio.
Worked examples
A slab 10 ft by 10 ft and 4 inches thick. 4 inches is one third of a foot, so the volume is 10 × 10 × 1/3 = 33.33 cubic feet. That is 1.235 cubic yards, or 0.944 cubic metres. With 10% for waste, order 36.67 cubic feet, which is 1.358 cubic yards or 1.038 cubic metres. An 80 lb bag makes about 0.60 cubic feet, so 36.67 ÷ 0.60 = 61.1, and you need 62 bags. At 150 lb per cubic foot the concrete weighs 5,500 lb.
One cubic metre of a 1 : 2 : 4 mix. The dry volume is 1 × 1.54 = 1.54 cubic metres. The ratio has 7 parts. Cement is 1.54 × 1 ÷ 7 = 0.22 cubic metres. At 1,440 kg per cubic metre that is 316.8 kg, or 6.34 bags of 50 kg. Sand is 0.44 cubic metres and stone is 0.88 cubic metres. With a water to cement ratio of 0.5, the water is 158.4 litres.
About bags and mix ratios
- The yield of a bag of premixed concrete is printed on the bag. Common figures on bags sold in the United States are 0.30 cubic feet for 40 lb, 0.45 for 60 lb and 0.60 for 80 lb.
- If you leave the yield blank, this tool uses 0.0075 cubic feet for each pound of dry mix. That matches the figures above, and gives about 9.4 litres for a 20 kg bag. Type the yield from your own bag if it is different.
- Common site mixes by volume of cement : sand : stone are 1 : 3 : 6, 1 : 2 : 4 and 1 : 1.5 : 3. In India these are widely used as the nominal mixes for grades M10, M15 and M20. M25 is often quoted as 1 : 1 : 2, but grades of M25 and above should use a designed mix.
- The dry volume factor of 1.54, the cement bulk density of 1,440 kg per cubic metre and the other mix values are common estimating figures. You can change every one of them.
Limits you should know
- This is a quantity estimate. It does not check strength, slab thickness, reinforcement, footing size or building rules. Ask an engineer or your building authority about structural work.
- A mix ratio is not a strength promise. A mix for a stated strength, such as 25 MPa or 3000 psi, must come from a mix design or a ready-mix supplier.
- The cost uses only the prices that you type. This tool holds no price data, and it leaves out delivery, labour, forms, reinforcement and tax.
- Real ground is uneven and forms can bulge, so the true volume can be higher. That is why waste is added.
- Bag yields, densities and bulk densities change with the product and with moisture. Use the figures from your supplier when you have them.
- It does not count concrete blocks, paving slabs or rebar, and it does not work out gravel, asphalt or sealer.