Toolvito

Works on this device

Research Timeline Planner

List the tasks of your study, how long each takes and which tasks must end first. The planner works out the critical path, the float of every task, the dates and a Gantt-style table you can print or download.

Enter your values

Your values

With a start date, every task gets a start and an end date.

Tasks

One row for each task, in any order. Duration 0 makes a milestone. In "Starts after tasks", type the numbers of the tasks that must end first, such as 1, 3.

This is off unless you turn it on. Saved entries stay in this browser only. Untick the box to delete them.

Your values are worked out in this browser. They are not sent to a server.

Your result will show here

Fill in the values, then choose Make the timeline.

How to use this planner

  1. Choose whether durations are in weeks, months or days. Type a start date if you want dates.
  2. Type one row for each task: its name, its duration, and the numbers of the tasks it starts after, such as 2, 3. A duration of 0 makes a milestone, such as a submission date.
  3. Choose Make the timeline. The result shows the project length, the critical path, a schedule with the earliest and latest starts, and a Gantt-style table.
  4. Copy or download the timeline as text, or download the page file to print. Tick "Save my entries on this device" to keep your tasks in this browser.

The method

  • Critical path method with finish-to-start links: a task starts when every task it starts after has ended.
  • Forward pass: earliest start = the latest earliest end of the tasks before it (0 when none); earliest end = earliest start + duration.
  • Backward pass: latest end = the earliest latest start of the tasks after it (the project end when none); latest start = latest end − duration.
  • Float = latest start − earliest start. Tasks with no float form the critical path: a delay to any of them delays the whole project.
  • Dates: the start date plus the time in days, weeks of 7 days, or calendar months.

Worked example

A study has a literature review (8 weeks), ethics approval (6), study design (4, after the review), a pilot (3, after ethics and design), recruitment (6), data collection (12), analysis (8) and writing (10), each after the one before, then a submission milestone.

The longest chain is 8 + 4 + 3 + 6 + 12 + 8 + 10 = 51 weeks, so the project takes 51 weeks. Ethics approval ends at week 6 but the pilot cannot start before week 12, so ethics has 6 weeks of float.

A draft of the introduction (6 weeks, after the design) can run from week 12 and has 33 weeks of float.

Limits you should know

  • Only finish-to-start links are used. A task that may start while another is still running needs to be split into parts.
  • Durations are whole numbers of your unit. Dates do not leave out weekends or holidays.
  • The planner assumes enough people and money for tasks that run at the same time; it does not level resources.
  • For a general project, the Project Timeline & Gantt Maker and the Critical Path Calculator are other pages of this site.