Project Timeline & Gantt Maker
List your tasks with their working days and the tasks they come after. The page works out every date, the float and the critical path, and draws the Gantt chart.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Make the chart.
Your result
How it was worked out
How to make a Gantt chart
- Choose Gantt chart from tasks and working days, or start from an example.
- Type each task with its working days. Type 0 for a milestone.
- In After tasks, type the numbers of the tasks that must end first, such as 2, 3. Write 2+3 to start 3 working days after task 2 ends, or 2-1 to overlap it by one day.
- Choose the project start and, under More options, your working days and days off.
- Press Make the chart, then download it in the box below.
How the dates are worked out
This is the critical path method. A task starts on the first working day after all the tasks it comes after have ended (plus any gap). The project ends when the last task ends.
Working back from the end gives the latest dates. Float is how many working days a task can slip without moving the end of the project. Tasks with no float form the critical path: if one of them is late, the whole project is late.
Worked example (the first example): Plan 3 days, Design 5 days after Plan, Build 10 days after Design, a guide of 4 days starting 2 days after Design, Test 5 days after Build, and the launch after the guide and the tests. From Monday 2 November 2026, Monday to Friday, the project takes 23 working days and ends on Thursday 3 December 2026; the guide has 9 working days of float.
Working days and days off
Choose Monday to Friday, Monday to Saturday, Sunday to Thursday, every day, or type your own working days. This tool knows no public holidays: type each day off as a date (year-month-day) in Days off.
PERT estimates
When you are not sure how long a task takes, give three numbers: the least (optimistic, O), the most likely (M) and the most (pessimistic, P). The expected time is (O + 4M + P) ÷ 6 and the spread (P − O) ÷ 6. The page gives the expected length of the project, a safe length at the confidence you choose, and the chance to finish by a deadline.
Limits you should know
- Tasks are linked finish to start, with a gap or an overlap in working days. Start-to-start and finish-to-finish links, and limits on people or machines, are not used.
- Up to 100 tasks and 5,000 working days.
- The chance from PERT uses the normal distribution, which is an approximation.
Privacy
The schedule is worked out and drawn in your browser. Only when you press Make the files, Make the PDF or Make the file is the chart (and, for a document, the result and its table) sent to the Toolvito server to make the file. Download the result within one hour after the job finishes. Choose Delete files now to request earlier removal. The hourly cleanup normally removes files within one to two hours after completion.