Calculates on this device. File exports run online.
Critical Path Calculator
List the activities of a project, how long each takes and what each must wait for. The calculator finds the critical path: the chain of activities that sets the length of the project, where any delay makes the whole project late. It also shows how much every other activity can slip (float), the dates on working days, and with three-point estimates the chance of finishing on time.
Enter your values
Check these values
This is off unless you turn it on. Saved entries stay in this browser only. Untick the box to delete them.
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose the button below them.
Your result
How it was worked out
How to use it
- Choose Critical path (CPM) and enter each activity with its duration. Under Comes after, write the activities it waits for, by name or row number, separated by commas.
- For other kinds of link write SS (starts after the other starts), FF (finishes after the other finishes) or SF, with a lag such as C SS+2 (two days after C starts) or D FS-1 (one day before D finishes).
- Press Find the critical path. Add a start date to get a date for each activity, on weekdays or every day, without holidays.
- With uncertain durations choose Three-point estimates (PERT) and give an optimistic, a most likely and a pessimistic duration for each activity.
How it is worked out
- Forward pass: an activity starts as early as all its links allow (early start); early finish = early start + duration. The project takes as long as the largest early finish.
- Backward pass: an activity finishes as late as its later activities allow (late finish); late start = late finish − duration.
- Total float = late start − early start. Free float = how far an activity can slip before it moves anything after it. The critical path is made of the activities with no float.
- PERT: mean = (optimistic + 4 × most likely + pessimistic) ÷ 6, standard deviation = (pessimistic − optimistic) ÷ 6. The project is read as a normal distribution along the critical path.
Limited resources
The critical path assumes every activity can start as soon as its links allow. When crews, machines or rooms are shared, write what each activity uses under Uses and what is available under Resources available, then use the box below: the solver finds the shortest plan in which no resource is overbooked and proves it is the shortest.