Energy Baseline Calculator
An energy baseline says how much energy a site used before a change, in a form that later periods can be compared with. This tool fits a straight line to your past energy against one driver, such as degree days or units made, and shows how well the line fits.
Enter your values
Check these values
This is off unless you turn it on. Saved entries stay in this browser only. Untick the box to delete them.
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose Baseline from energy and one driver.
- Add one row for each past period, such as a month. Type the driver of that period, for example its heating degree days or its output, and the energy used. You can also paste rows from a spreadsheet.
- Type the unit of the energy and the name of the driver, so that the result reads well.
- Choose Calculate. The result shows the slope, the base load and R squared, a table of every period against the baseline, and a chart.
- Choose Use this baseline for new periods to work out the energy that the baseline expects for other driver values.
- Try an example fills the empty rows with example values, so that you can see how an option works.
- Tick Save my entries on this device to keep your rows for your next visit. Download my entries gives you a file that you can open here again.
What each option does
- Baseline from energy and one driver: the least squares line energy = slope × driver + base load, with its measures of fit.
- Expected energy from a baseline line: for a slope and a base load that you already have, the expected energy of new periods.
- Baseline without a driver: the total, the average for a day and the figure for a year, for energy that follows no clear driver.
The formulas
- x is the driver of a period and y its energy. Slope = Σ(x − mean x)(y − mean y) ÷ Σ(x − mean x)².
- Base load = mean y − slope × mean x. It is the energy of a period when the driver is 0.
- R squared = 1 − Σ(y − baseline)² ÷ Σ(y − mean y)². It is the share of the changes in energy that the line explains, from 0 to 1.
- Standard error = √(Σ(y − baseline)² ÷ (number of periods − 2)). CV(RMSE) = standard error ÷ mean energy.
- Expected energy of a new period = slope × driver + base load.
Worked example
Three periods have drivers of 1, 2 and 3 and used 2, 3 and 5 units of energy. The mean driver is 2 and the mean energy is 3.3333. The slope is 3 ÷ 2 = 1.5, and the base load is 3.3333 − 1.5 × 2 = 0.3333.
The baseline gives 1.8333, 3.3333 and 4.8333 for the three periods. The squares of the differences add up to 0.1667, and the squares of the distances from the mean add up to 4.6667. So R squared is 1 − 0.1667 ÷ 4.6667 = 0.9643, and the standard error is √(0.1667 ÷ 1) = 0.4082.
With a slope of 9.5 kWh for each degree day and a base load of 3,200 kWh, a month with 350 degree days is expected to use 9.5 × 350 + 3,200 = 6,525 kWh.
Where the terms come from
Energy baseline (EnB) is a term of ISO 50001, the standard for energy management systems. A baseline that follows a driver is often called a normalised or adjusted baseline. CV(RMSE) is a measure of fit that is used in guides for the measurement and verification of savings. This tool does the arithmetic only. It holds no limit value of any standard, and it does not check a management system.
Limits you should know
- A straight line with one driver is a simple model. Many sites need two drivers, or a line that changes its slope at some point. This tool does not fit those.
- The line holds only inside the range of driver values in your data, and only while the site, its equipment and its hours stay as they were.
- A high R squared does not prove that the driver is the cause. Look at the table and the chart for single periods that lie far from the line.
- Use periods of the same length that cover a whole year or a whole production cycle. With few periods, one more period can change the line a lot.
- Saving is off unless you tick Save my entries on this device. Saved rows stay in this browser only. Clearing the data of your browser removes them, so keep your own copy with Download my entries.
- The values that Try an example fills in are made up. They describe no real site.