The reorder point is the stock level at which you order again, so that the new goods arrive before you run out. Enter your average demand, the lead time and the safety stock, and the calculator gives the reorder point in units and in days of cover.
Enter your values
Check these values
Your values are worked out in this browser. They are not sent to a server.
Your result will show here
Fill in the values, then choose Calculate.
Your result
How it was worked out
How to use this calculator
- Choose the time unit: days, weeks or months. Enter demand per period and the lead time in the same periods.
- Enter the safety stock in units, or as a number of days of demand.
- Choose Calculate. Order again when the stock on hand plus the stock already on order falls to the reorder point.
- If you do not know the safety stock, choose Reorder point with safety stock from a service level and enter how much demand or lead time varies.
- For the reorder level, minimum, maximum and average stock levels of cost accounting, choose Reorder level, minimum and maximum stock levels.
The formulas
- Reorder point = average demand × average lead time + safety stock.
- Cover at the reorder point = reorder point ÷ average demand per period.
- Safety stock from a service level: z × σd × √L when demand varies, z × d × σL when the lead time varies, and z × √(L × σd² + d² × σL²) when both vary. z comes from the cycle service level, such as 1.6449 for 95%.
- Reorder level = highest demand × longest lead time. Minimum level = reorder level − average demand × average lead time. Maximum level = reorder level + reorder quantity − lowest demand × shortest lead time. Average stock level = minimum level + reorder quantity ÷ 2.
Worked example
A shop sells 40 units a day on average, and an order takes 9 days to arrive. It keeps a safety stock of 120 units. The demand during the lead time is 40 × 9 = 360, so the reorder point is 360 + 120 = 480 units. That is 12 days of cover.
With a standard deviation of demand of 8 units a day and a 95% cycle service level, the safety stock is 1.6449 × 8 × √9 = 39.48 units, and the reorder point is 399.48 units.
With demand of 25 to 55 units a day (average 40), lead times of 6 to 13 days (average 9) and a reorder quantity of 500, the reorder level is 55 × 13 = 715. The minimum level is 715 − 360 = 355, the maximum level is 715 + 500 − 25 × 6 = 1,065, and the average stock level is 355 + 250 = 605.
Limits you should know
- The reorder point is compared with the stock on hand plus the stock on order. If you count only the stock on the shelf, you may order twice.
- Use the same time unit for demand and lead time.
- Safety stock lowers the chance of a stockout. It cannot remove it. The Safety Stock Calculator has more methods.
- How much to order each time is another question: use the Economic Order Quantity Calculator.